darwink
Senior Member
^ It was a joke. There is literally no reason to do a commuter rail fantasy map besides station locations
^ It was a joke. There is literally no reason to do a commuter rail fantasy map besides station locations
^ It was a joke. There is literally no reason to do a commuter rail fantasy map besides station locations
Great map! You forgot to add the Providence spur off the south line.
Project | Project Type | Trips | Net Op Costs | Capital Costs | NPV 3.05% $ per incremental Trip (lower is better) | Comments |
Beddington to North Pointe | Green Line LRT | 11500 | $0 | $0 | $0 | Screened out: improbable estimate; dependent on other unplanned segment |
96 Ave to North Pointe | Green Line LRT | 6000 | $1 | $0 | $3,246 | Screened out: improbable estimate; dependent on other unplanned segment |
MAX Purple/17 Ave SE - 52 St E to 84 St SE | BRT | 3300 | $0 | $43 | $11,850 | Selected: Serves Developing Communities, Low Relative Cost, Leverages Existing Infrastructure |
52 Street E BRT -Saddletowne to Seton | BRT | 20500 | $15 | $60 | $16,796 | Selected: Connects Communities to Jobs, Connects MAX Orange, Green Line and Blue Line, Low Relative Cost, Leverages Existing Infrastructure |
40 Ave to 64 Ave | Green Line LRT | 19000 | $1 | $300 | $16,814 | Screened out: dependent on other unplanned segment |
Route 305 West | BRT | 6700 | $7 | $30 | $25,696 | Selected: Low Relative Cost |
NW-HUB / West Campus Mobility | BRT | 4220 | $5 | $22 | $29,672 | Selected: Alternative Option Examined (BRT Orange realignment to Lions Park) |
162 Ave BRT - Somerset Bridlewood Station to Providence | BRT | 6500 | $6 | $95 | $32,592 | Screened out: Needs additional study, beyond 2030 |
Red Line S - Extension to 210 Ave S | LRT | 14700 | $9 | $341 | $35,518 | Screened out: Needs additional study, beyond 2030 |
Shaganappi HOV - Bowness Road to Stoney Trail | HOV/BRT | 8000 | $6 | $179 | $37,224 | Screened out: Needs additional study |
16 Ave N to 64 Ave N | Green Line LRT | 26900 | $8 | $850 | $37,390 | Selected: Most cost efficient Green Line extension; serves Bus transfer station at 64th |
16 Avenue N to North Pointe | Green Line LRT | 42300 | $6 | $1,500 | $38,223 | Screened out: improbable estimate |
North Regional Context Study/144 Ave N BRT - Tuscany to Nose Creek | BRT | 10800 | $21 | $42 | $42,477 | Screened out: Needs additional study, beyond 2030 |
16 Ave N to 96 Ave N | Green Line LRT | 36300 | $5 | $1,500 | $44,005 | Screened out: 2nd best Green Line Project: improbable estimate |
MAX Purple/17 Ave SE - 84 St E to City Limits | BRT | 2200 | $2 | $71 | $45,551 | Screened out: beyond 2030 |
Blue Line NE - 88 Ave to 128 Ave NE | LRT | 9700 | $2 | $405 | $46,370 | Screened out: dependent on other unplanned segment, beyond 2030 |
Westbrook to MRU Streetcar | Streetcar | 9400 | $9 | $292 | $50,331 | Screened in: Additional study ordered to examine alternatives including routes which could serve Currie Barracks neighbourhood and Marda Loop; no commitment for construction due to need for additional study |
Blue Line NE -Saddletowne to 88 Ave NE | LRT | 3500 | $1 | $158 | $50,707 | Selected: Serves Developing Communities, Low Relative Cost, Leverages Existing Infrastructure |
16 Avenue N to Beddington | Green Line LRT | 30800 | $6 | $1,500 | $52,495 | Screened out: improbable estimate |
Blue Line NE - 128 Ave to Stonegate NE | LRT | 3700 | $2 | $160 | $55,875 | Screened out: dependent on other unplanned segment, beyond 2030 |
Airport Transit Connector – Blue Line to Airport | LRT | 13000 | $7 | $600 | $56,340 | Screened out: beyond 2030 |
MAX Purple/17 Ave SE -Blackfoot Truck Stop to Downtown/Green Line | BRT | 1980 | -$2 | $156 | $62,067 | Screened out: beyond 2030, wait for Green Line completion |
16 Avenue N to 40 Avenue N and Shepard to Auburn Bay/Mahogany | Green Line LRT | 15200 | $5 | $850 | $62,327 | Screened out: doesn't reach 64th Ave Transfer Station |
64 Ave to 96 Ave | Green Line LRT | 9400 | -$3 | $650 | $62,934 | Screened out: dependent on other unplanned segment, beyond 2030 |
Shepard to McKenzie Towne | Green Line LRT | 4200 | -$3 | $325 | $63,471 | Selected: Best Green Line South extension; serves communities |
Auburn Bay/Mahogany to Seton | Green Line LRT | 5300 | $2 | $300 | $63,953 | Screened out: dependent on other unplanned segment, beyond 2030 |
Max Teal/South Crosstown BRT - Extension to 68 St E | BRT | 1500 | $5 | $7 | $64,121 | Selected: Low relative cost, low upfront costs mean if project fails to meet ridership expectations, project can be reexamined, Connects Greenline, and 52nd St E BRT, generating benefits far beyond the project in isolation, which is what is projected in this project screen |
Shepard to Seton | Green Line LRT | 12600 | -$1 | $850 | $65,915 | Screened out: too high of a budget for too low of ridership against competing projects; beyond 2030 |
Shepard to Auburn Bay/Mahogany | Green Line LRT | 7300 | -$3 | $550 | $67,339 | Screened out: too high of a budget for too low of ridership against competing projects; beyond 2030 |
Airport Transit Connector – Green Line to Airport | LRT | 9500 | -$3 | $750 | $72,388 | Screened out: dependent on other unplanned segment, beyond 2030 |
McKenzie Towne to Auburn Bay/Mahogany | Green Line LRT | 3100 | $0 | $225 | $72,581 | Screened out: too high of a budget for too low of ridership against competing projects; beyond 2030 |
16 Avenue N to 40 Ave N | Green Line LRT | 7900 | $7 | $550 | $86,876 | Screened out: high cost per rider due to commuity stations only |
64 Ave to Beddington | Green Line LRT | 3900 | -$2 | $650 | $156,680 | Screened out: dependent on other unplanned segment, beyond 2030 |
Blue Line W – Extension to 85 St SW | LRT | 1500 | $5 | $213 | $212,108 | Screened out: worst project financially |
Very cool, thanks! Was there a main source you used to compile that info or is it too split up? If you have a link that would be great as I could use it as a resource.Awesome! Always cool to see.
Here is some work I did that might help you think about this a bit more. All the numbers are sourced from city documents, and some are very rough estimates, as noted in comments. a key one to look at how much service might cost is the max teal extension - Operating costs of a Max service are about $1 million a KM. Of course, costs can be recovered elsewhere for a big change like this, but it gets into the old transit fight between coverage and frequency.
~snippy snip ~~
All drawn from the below - some green line projects you had to do math as they didn't present all the phasing options as discreet projects. And the NPV is own work.Very cool, thanks! Was there a main source you used to compile that info or is it too split up? If you have a link that would be great as I could use it as a resource.
The main culprits of the "connecting the grid" challenges are the river valleys, big hills, the railway, and Deerfoot - meaning any connection across them would probably cost a lot of money to complete.When trying to turn routes into lines and connect the grid, were there any places where it just gets messy and inefficient in your opinion?