Green Line LRT | ?m | ?s | Calgary Transit

Go Elevated or try for Underground?

  • Work with the province and go with the Elevated option

    Votes: 49 79.0%
  • Try another approach and go for Underground option

    Votes: 9 14.5%
  • Cancel it altogether

    Votes: 1 1.6%
  • Go with a BRT solution

    Votes: 3 4.8%

  • Total voters
    62
Hi All,
So $1.5 Billion is NOW (?) being Committed by the Feds for the Green Line. I Might have missed Something but IT was my understanding that the Funds were in Place a
Good While Back by the Libtards, Why Now? Edmonton gets cash for projects so Calgary has to get Something to Make Up? Sounds Like it to Me. My Origional Understanding was that All the Funding was in Place to Cover the WHOLE Green Line from North to South. To Just Cover a Portion and NOT the Whole Project means We Pay More at Higher Costs Later. Just how I feel about this Project due to the Fact they must HAVE KNOWN back then that Funding for the Whole Project Was NOT in
Place so in Theory they Lied to the Taxpayers. Not Good.

Tnx,
Operater,
 
Hello from Edmonton!

I was just wondering if the green line is close to approval yet?
 
Hello from Edmonton!

I was just wondering if the green line is close to approval yet?

It was approved like years ago. The final decisions on routing were made a year ago, and all funding was secured last summer. The recent news about the federal funding was mostly just a photo-op for the politicians involved.
 
It was approved like years ago. The final decisions on routing were made a year ago, and all funding was secured last summer. The recent news about the federal funding was mostly just a photo-op for the politicians involved.
Oh ok so is it under construction or will it be soon?
 
Soft construction is underway, so like site prep for the entire line, and the hard construction (tunnelling through downtown, track construction) will start in 2020.
 
Soft construction is underway, so like site prep for the entire line, and the hard construction (tunnelling through downtown, track construction) will start in 2020.

Has the city acquired all the land needed for the project yet?
 
Here's a question for the experts. What happens if somebody doesn't sell their land to the city? Is there some sort of legal procedure to make them sell the land?
 
Here's a question for the experts. What happens if somebody doesn't sell their land to the city? Is there some sort of legal procedure to make them sell the land?
Expropriation.
upload_2018-5-24_10-8-28.png

http://www.calgary.ca/Transportation/TI/GreenLineDocuments/GL-Land-Aquisition-FAQ-apr2016.pdf
 

Attachments

  • upload_2018-5-24_10-8-28.png
    upload_2018-5-24_10-8-28.png
    24.2 KB · Views: 449

Back