Video of the Green Line construction industry event that was held the other day.

A few tidbits from the video I wasn't aware of before. Opening day is being targeted as June 30, 2031. It kind of sounds like that might be between Shepard and the Event Centre station, not necessarily 7th Ave. Also, each LRV needs to have 1,000km of testing prior to being put into service so track work is planned to be built from the south to the north to allow LRV testing to begin while construction continues on the rest of the project.

 