O-tac
Active Member
Yeah I wonder the same thing.
The knee-jerk move is that of the UCP, the city needs to make sure it's not going to spend any more money on something if it's just going to be torn up by the provincial government.The City "winding down" the Green Line project doesn't seem like the best approach. Wouldn't it be better to see what the Province comes up with and then vote on that proposal in Council? The current approach seems like a knee-jerk, reactionary move that isn't well thought out regarding its consequences.
Ya it would seem a lot more prudent to preserve the team and governance structure that they finally established for at least a little bit longer. I think the assembled expertise could be redirected in a few directions, such as developing a proposal for a provincial-backed delivery model for mega-projects like this. There was some discussion about this in the July 30 council meeting and the desire to shift the cost-overrun burden to the province instead of the city.The City "winding down" the Green Line project doesn't seem like the best approach. Wouldn't it be better to see what the Province comes up with and then vote on that proposal in Council? The current approach seems like a knee-jerk, reactionary move that isn't well thought out regarding its consequences.
the LRV, in theory, could still be useful?
I don’t recall a red line spur ever discussed as an option. It would make sense in a lot of ways, but I don’t think the 7th ave capacity is there.I apologize in advance if this question has been asked recently, but I didn’t see it in one of the previous posts and I didn’t want to go back and read 100 pages of posts over the past year.
My question is whether the Green Line planners looked at having a spur coming off of the red line south? For example, a spur down Anderson Road into Quarry Park and then turning south east over to McKenzie town, etc.
I’m under the assumption they would’ve but I can’t find any mention of it.
Thanks, D
C$ 1B is not lost as it has been expended upon design, procurement and placing supply chain contracts to date. If all things were equal, without Alberta interfering, there would be: no negotiating breaches/ terminations of contracts; design issues; staff terminations; liquidating a company; re-designs etc. All that would apply would be a value for escalation which is a valid clause for a project over 2 years in duration. The value to be applied is calculated quarterly. In the execution phase: there will be further design value engineering, innovation and lean construction. With risk and reward, the Contractor's cost per design element is allocated as a an agreed target cost: whatever the underspend or overspend is, a shared %age value is applied which either means a bonus or deduction in value which either benefits or penalises both parties.The 1 Billion lost is equal to the money needed to extend the current plan to Shepard.
We are going to spend basically the same amount to get something worse.
They could also be sold to hipsters as tiny homes, or used as an exhibit in a museum of planning follies..a chain of...restaurants, you say?
I would argue a lot of that is lost at this point if we don't build anything. Design is worthless if you don't proceed with the project scope, land acquisitions and utility relocations don't matter if you don't proceed or choose a different right of way, etc...C$ 1B is not lost as it has been expended upon design, procurement and placing supply chain contracts to date. If all things were equal, without Alberta interfering, there would be: no negotiating breaches/ terminations of contracts; design issues; staff terminations; liquidating a company; re-designs etc. All that would apply would be a value for escalation which is a valid clause for a project over 2 years in duration. The value to be applied is calculated quarterly. In the execution phase: there will be further design value engineering, innovation and lean construction. With risk and reward, the Contractor's cost per design element is allocated as a an agreed target cost: whatever the underspend or overspend is, a shared %age value is applied which either means a bonus or deduction in value which either benefits or penalises both parties.
Look forward to a further breakdown but out of the 1.85 Billion I wonder how much is truly lost. The design has to be some of the smaller numbers, right? The utility work, land acquisition, and the LRV, in theory, could still be useful?
City officials also said Calgary may be open to litigation from contractors because of broken agreements, although it's unclear to what extent.
Almost 250 employees and consultants were involved in the Green Line on behalf of the city, and about 800 staff were brought in as contractors. There are more than 70 contracts that need to be addressed as a part of the wind-down.
I'm not referring to the money that was actually spent on something (some of that can be considered lost as well). According to the article there is nearly 1 billion in wind down cost.C$ 1B is not lost as it has been expended upon design, procurement and placing supply chain contracts to date. If all things were equal, without Alberta interfering, there would be: no negotiating breaches/ terminations of contracts; design issues; staff terminations; liquidating a company; re-designs etc. All that would apply would be a value for escalation which is a valid clause for a project over 2 years in duration. The value to be applied is calculated quarterly. In the execution phase: there will be further design value engineering, innovation and lean construction. With risk and reward, the Contractor's cost per design element is allocated as a an agreed target cost: whatever the underspend or overspend is, a shared %age value is applied which either means a bonus or deduction in value which either benefits or penalises both parties.
You forget that certain contracts are in place: build or not build? Negotiation is key and creative discussions may see Contractors be considered for other projects. There always is middle ground and this is not unusual in megaprojects. There is a key negotiation point: the existing 60% design. Who owns that design presently; what does the design contract state? You would give anything to be a fly on the wall in that bun fight!I would argue a lot of that is lost at this point if we don't build anything. Design is worthless if you don't proceed with the project scope, land acquisitions and utility relocations don't matter if you don't proceed or choose a different right of way, etc...
That is a worst case scenario. Assume that Alberta wants to redesign. Effectively, a 75% staff reduction would be immediately effective (Contractors, self-employed, local staff etc.). 25% staffing is sufficient to calculate termination costs in conjunction with legal teams. Negotiating termination contracts of awarded contracts. What does the contract cover? Overheads and lost profits, reimbursement of insurances, placing of sub-contracts of any tier? The list is endless. A shrewd developer will have covered loss of profit and overheads: you may have a contract but you have not fulfilled obligations to secure insurances etc., without them, you have not complied with the contract - no cost. C$ 1B is an outside possibility but heavy negotiations are an art form.I'm not referring to the money that was actually spent on something (some of that can be considered lost as well). According to the article there is nearly 1 billion in wind down cost.