darwink
Senior Member
In Q2 of 2017, they thought they were at a Class "D" estimate. They had top of rail and alignment for the entire project. Council started fooling around with the alignment immediately, a recommendation for further investigation and the project team didn't push back! On top of it all, their procurement strategy was leisurely at best. With the benefit of hindsight the signs of an out of control project were there even then.