Five tower development for Calgary's Eau Claire Market
Tower 1, at 35 storeys and ~135 meters will be office.
Tower 2, at 25 storeys and ~100 meters will be mixed use (hotel/residential)
Tower 3, at 20 storeys and ~80 meters will be residential.
Tower 4, at 15 storeys and ~50 meters will be residential.
Tower 5, at 13 storeys and ~45 meters will be residential.
The Land Use Amendment has been submitted, with the DP currently being worked on as well. The project is expected to start in early 2015, and will take 7 - 10 years to complete all phases.
Here are some renderings...
http://www.crebnow.com/harvard-developments-to-redevelop-eau-claire-market/
http://globalnews.ca/news/980340/gallery-major-overhaul-planned-for-eclectic-eau-claire/
http://news.buzzbuzzhome.com/2014/01/hottest-calgary-developments-2013.html
Tower 1, at 35 storeys and ~135 meters will be office.
Tower 2, at 25 storeys and ~100 meters will be mixed use (hotel/residential)
Tower 3, at 20 storeys and ~80 meters will be residential.
Tower 4, at 15 storeys and ~50 meters will be residential.
Tower 5, at 13 storeys and ~45 meters will be residential.
The Land Use Amendment has been submitted, with the DP currently being worked on as well. The project is expected to start in early 2015, and will take 7 - 10 years to complete all phases.
Here are some renderings...

http://www.crebnow.com/harvard-developments-to-redevelop-eau-claire-market/

http://globalnews.ca/news/980340/gallery-major-overhaul-planned-for-eclectic-eau-claire/