Calgary

MacKimmie Complex and Professional Faculties Building Redevelopment | 59m | 15s | U of C | DIALOG

UrbanWarrior

Senior Member
Member Bio
Joined
Mar 28, 2016
Messages
2,545
Reaction score
4,317
Location
Capitol Hill
Considering the substantial amount of structural work going on here, I feel like this project deserves a dedicated thread. The tower crane has now been installed, and the removal of the exterior and interior of the building down to the superstructural steel will now commence.

The building is being expanded from 13 to 15 storeys, making it once again the tallest building on the U of C campus, and the Canada Green Building Council is hoping it will be one of the most environmentally sustainable buildings on the continent when complete.


https://www.cagbc.org/CAGBC/Zero_Carbon/mackimmie_profile.aspx


Taken today by me...

fullsizeoutput_8ec.jpeg
 

Attachments

darwink

Senior Member
Member Bio
Joined
Oct 7, 2016
Messages
1,056
Reaction score
1,321
MacKimmie Complex and Professional Faculties Building plans to be revealed at open house
Campus community invited to a sneak peek March 28

https://www.ucalgary.ca/utoday/issue/2018-03-19/mackimmie-complex-and-professional-faculties-building-plans-be-revealed-open-house

Look up! Construction crane to begin removing MacKimmie Tower's exterior panels March 19
MacKimmie Complex and Professional Faculties Building Redevelopment project update

https://www.ucalgary.ca/utoday/issue/2018-03-12/look-construction-crane-begin-removing-mackimmie-towers-exterior-panels-march-19

Today:
upload_2018-3-19_14-32-49.png
 

Attachments

Last edited:

Oddball

Senior Member
Member Bio
Joined
Mar 18, 2016
Messages
1,132
Reaction score
1,051
I didn't know PF was gonna be a part of this. I was already really interested in this project now I really can't wait to see what they have in mind.
 

darwink

Senior Member
Member Bio
Joined
Oct 7, 2016
Messages
1,056
Reaction score
1,321
Social work is moving out of PF in fall 2019, and the remaining faculties will expand into the space. In addition, it should free up a floor or two in math sciences and earth sciences by moving administrative units from academic and lab capable buildings to the upper floors of this project. It will also collect small bits and pieces from elsewhere in the university.
 

Mountain Man

Senior Member
Member Bio
Joined
Mar 9, 2017
Messages
1,287
Reaction score
1,089
Are there any renders of what it will look like? Also, I can see the crane from my office downtown.
 

UrbanWarrior

Senior Member
Member Bio
Joined
Mar 28, 2016
Messages
2,545
Reaction score
4,317
Location
Capitol Hill
No, the design is being released at the open house on the 28th.
 

maestro

Senior Member
Member Bio
Joined
Apr 23, 2007
Messages
6,941
Reaction score
1,761
Early concepts from 10 years ago were all glass. It will be interesting to see how much this has changed.
 

UrbanWarrior

Senior Member
Member Bio
Joined
Mar 28, 2016
Messages
2,545
Reaction score
4,317
Location
Capitol Hill
All glass, but different. Double facade breaks the current lines. Early sketches looked like a crumpled paper mache black potato. I am told newer ones are better.
Ouuuuu I'm excited! :D
 