Now going to be a high rise residential project.

A2.jpg




Was originally going to be two 14 floor office towers.

Original renderings
9372845051_907f819e14_b.jpg9375621002_f58d4e1bde_b.jpg
 
Last edited:

Always_Biking

Senior Member
Member Bio
Joined
Nov 4, 2015
Messages
1,269
Reaction score
897
I've heard that they may only build the first two or three floors where all the retail is and then pause. I hope not, but if they do I'm still so happy that this started construction again and it won't sit as a concrete pit.
 

Daveography

Moderator
Member Bio
Joined
Sep 22, 2015
Messages
7,702
Reaction score
9,916
Location
Edmonton, Alberta, Canada
@Always_Biking I always hear that rumour about at least one major development in Alberta during a downturn (the same was said about The Bow, and about EPCOR tower here in Edmonton), but I've yet to see it actually happen. Things might be different for buildings being built on spec (not sure if that's the case for Place 10), but I'm always very skeptical of those kinds of rumours.
 

Habanero

Active Member
Member Bio
Joined
Feb 15, 2016
Messages
347
Reaction score
251
Location
Calgary
Yes indeed, hard to see what's actually going to happen with this but I think if the worst case scenario is the podium being built I guess that would be OK that's the best part of the building.

I had heard that these were to be built on spec so if they did get capped off at the top of the podium it wouldn't be a surprise.
 

Ramako

Moderator
Member Bio
Joined
Oct 30, 2007
Messages
4,623
Reaction score
714
Location
Toronto, ON
Will the podium for these towers integrate at all with the new Marriott to the west in terms of some kind of ground floor or underground concourse, or ground level programming?
 

maestro

Senior Member
Member Bio
Joined
Apr 23, 2007
Messages
6,983
Reaction score
1,776
@Always_Biking I always hear that rumour about at least one major development in Alberta during a downturn (the same was said about The Bow, and about EPCOR tower here in Edmonton), but I've yet to see it actually happen. Things might be different for buildings being built on spec (not sure if that's the case for Place 10), but I'm always very skeptical of those kinds of rumours.
Agreed. Does seem strange that no forms or completed columns appear above the ground floor in the last update.
 

Surrealplaces

Moderator
Member Bio
Joined
Sep 24, 2015
Messages
6,533
Reaction score
13,087
Location
Calgary
Will the podium for these towers integrate at all with the new Marriott to the west in terms of some kind of ground floor or underground concourse, or ground level programming?
No integration to the Marriott from what I can tell. They are separated by 5th street, which dips down so as to go underneath the train tracks, so underground is probably out.
 

Surrealplaces

Moderator
Member Bio
Joined
Sep 24, 2015
Messages
6,533
Reaction score
13,087
Location
Calgary
Agreed. Does seem strange that no forms or completed columns appear above the ground floor in the last update.
Yup, no action on top of the podium, only work going on inside of it. Which makes sense given that it was office space built on spec. Maybe when they do build the upper portion later there will be a new design that's a bit nicer. This design is okay, but pretty bland.
 