  1. Levelmind

    The Royal | 114.9m | 34s | Embassy Bosa | Abugov Kaspar

    2 of the excavators were broken down today.
  2. Levelmind

    The Royal | 114.9m | 34s | Embassy Bosa | Abugov Kaspar

    There are steel I beams behind the upper anchor bolts.
  3. Levelmind

    The Royal | 114.9m | 34s | Embassy Bosa | Abugov Kaspar

    Aug 4th is the date right now for the first crane to be set up but I think it will be the following week.
  4. Levelmind

    The Royal | 114.9m | 34s | Embassy Bosa | Abugov Kaspar

    Back in mid January some of the top couple rows of anchor bolts holding back the Shotcrete shoring excavation started popping out. This is the main reason why this job is taking so long.
  5. Levelmind

    The Royal | 114.9m | 34s | Embassy Bosa | Abugov Kaspar

    They brought in a 5th excavator this morning.
  6. Levelmind

    The Royal | 114.9m | 34s | Embassy Bosa | Abugov Kaspar

    The crane erection is still 3-4 weeks away if not longer.