After the roof is on the podium the cranes come down then change the location of the cranes that would sit on the roof slab for the Towers.
That way the retail will be open during the rest of the construction.
Would be the same time we want the first crane up as soon as possible to be able to use it to pour concrete.
The plan is to have 3 cranes up for the parkade and podium.
With a least 2 placing booms.
They hope to start digging the crane pad bye the end of this week.
Then pouring the crane base early next week. I'd guess the earliest date that the 1st crane going up would be August 15th....