The Barron | 43m | 11s | Strategic Group | Gibbs Gage

With the addition of the extra two floors, the design has changed. There's been no updated render shown here of the front, only the back.
 
So the penthouse is getting enveloped? That's too bad, thought that would make a great VRBO lol.
The penthouse was demolished. The two new floors are almost structurally complete.
 
IMG_6698.jpeg
 
Next week the new Council will be looking at the budget for the year. Note that this is just the final year of the 4-year overall budget passed in 2022. The document outlining everything can be found here:

Why is this relevant to this thread? Well, I saw this tidbit in there, and I can't remember if this is something that was previously announced, or is this a new public contribution to this project (page 10)?
1762373451472.png

1762373480462.png


So, $7.5 million from the City if this gets Council approval.
 
Next week the new Council will be looking at the budget for the year. Note that this is just the final year of the 4-year overall budget passed in 2022. The document outlining everything can be found here:

Why is this relevant to this thread? Well, I saw this tidbit in there, and I can't remember if this is something that was previously announced, or is this a new public contribution to this project (page 10)?
View attachment 693456
View attachment 693457

So, $7.5 million from the City if this gets Council approval.
That's been the deal for several years now. Because they are getting more per square foot than the office conversion program allows, the city had to create a separate grant for them, but similarly, they don't get the money until the building is finished, which is why it's showing as 2026 I assume.

Article from 2021 when the city announced the funding:
 